CCC是证明屋子已经照着原图建筑完毕。
可是,屋子里的水电供是否已经是俱全并不是ccc里的条件
发展商只要把水电供需要的设施根据要求建起来就算完工,因为水电供会由service provider哪里接手的。
而service provider自己内部问题而迟发放屋子的水电供并不是发展商的责任
另附一段FAQ给你参考
===================
Q: Can I claim LAD until the date when electricity supply is actually provided?
A: Please read and understand the definition of "ready for connection" in your Sale and Purchase Agreement. Thereafter, write to TNB for their written confirmation as to where the fault is and the party that is attributing to the delay of supply being available. With the documentary evidence, you could then substantiate your claim that the Developer has prematurely delivered vacant possession to you and thus your claim for LAD. ===================
|