1) 首先是town planner 和 architect 先进,他们会先submit给local council拿 development order (DO) / Kebenaran Merancang (KM) <---最重要,没这个approval,说什么engineering design都是废话。
2) 只有拿到development order 的时候,C&S, M&E consultant才会进来做detail engineering submission。Architect同时也会做building plan submission。
2.1) C&S consultant submit Earthwork, Road and drainage, external water supply, external sewerage图给各个相关部门(e.g. local council, JPS, JKR, JBA, IWK, etc.)。
2.2) M&E consultant submit for street lighting, internal water supply, internal plumbing, bomba, TNB 等等
2.3) Architect submit building plan to local council
3) 当earthwork 拿到 approval时, site 就可以开工 (不需要等全部approval)
现在有些地方政府要EIA approval before 给 DO approval。所以EIA consultant要submit EIA report to DOE拿approval,然后local council才会给 DO Approval。
一定要有 development order approval 才可以做 detail engineer submission,不然 authority 不理你 (但是现在又些地方政府开始实行 DO + Detail Engineering一起做submission)。
这是西马的。
|
|