深重打擊!建築商撤出檳海底隧道工程;到底什麼原因讓吃到口裡的肥肉也吐回出來?
[复制链接]
|
|
深重打擊!建築商撤出檳海底隧道工程;到底什麼原因讓吃到口裡的肥肉也吐回出來?
事有蹺蹊,建築商應該聞到不妥,寧願撤出,也不要涉及貪污,被反貪會調查影響整個公司集團的聲譽。
According to The Star, some issues that are making it difficult for Mudajaya to execute the project include the inability to secure the exact date for the site possession, the uncertainty in signing the construction contract, and insufficient information provided for the project which has resulted in a lapse of time to the timelines in the letter of award. The Works Ministry has said it has yet to receive the feasibility studies and detailed design for the undersea tunnel after an 18-month wait.
Works Minister Datuk Seri Fadillah Yusof reportedly said the delay in submitting the reports, that costs RM305 million, was “very unusual” as the project was awarded to the project delivery partner in April 2013.
新聞背景:
|
|
|
|
|
|
|
|

楼主 |
发表于 11-11-2017 09:36 PM
|
显示全部楼层
繼北京城建 BUCG 後,又一大建築商撤出工程了。 |
|
|
|
|
|
|
| |